nust
 
Development works of NUST Campus -12 were awarded to FWO in Jun 2005. The total cost of this project was 4.38 Million US$. The project included roads, water supply system, sewerage and drainage system for the NUST campus and accommodation for its employees. The project was completed in April 2008.
dhanna
 

Create efficient management system for water sources.

Provide portable water to the locals in the area.

Harness seasonal runoff to provide additional water for irrigation.

Conserve and recharge ground water table.

It is designed to facilitate the catchment area of 13000 acre.

 
 
Project Details

 Proj Name:  Construction of Dhana Irrigation and water Supply Scheme
 Proj Location within  Country: FATA (KPK)
 Name of Client / Sponsor: FATA Sectt
 Consultant:  USAID
 No of Plants Employed: 138
 Start Date (Month / Year): Feb 2013
     
 Country:  Pakistan
 Scoop of Work: Earth Work / Stone Pitching / RCC Slab / Beam / Columns / Steel Structure / Pipe Line
   
 Name of Associated  Firm (s) Nil
 Total Project Cost:  Rs 1625 Mn
 Completion Date
Oct 2015
 
 
  • dhana-irr
  • dhana-irri
  • dhanna
  • dhanna1
 OPF
 

To cater for the housing needs of Overseas Pakistanis and to provide them residential facilities, OPF has planned and established a number of housing schemes in different cities of the country. Thousands of plots created in these schemes were allotted to Overseas Pakistanis. These schemes are located at the prime locations in the cities of Islamabad, Lahore, Gujrat, Peshawar, Dadu, Larkana and Mirpur (AJK). OPF Valley Zone-V Islamabad is located on Japan road alongside the Sawan River, about 24 kilometers from Zero Point. The scheme has been planned over an area of 5000 kanals. The Master plan of the scheme was prepared by M/s NESPAK and approved by CDA. Adequate educational and recreational facilities including lakes, parks, amenities club etc, have also been planned in the scheme.

Project Details

 Proj Name:  Dev of OPF Housing Scheme Zone-V Islamabad (Package-I)
 Proj Location within  Country: Islamabad
 Name of Client / Sponsor: OPF
 Consultant:  Engg Associates Pvt Ltd
 No of Plants Employed: ---
 Start Date (Month / Year): Sep 2008
     
 Country:  Pakistan
 Scoop of Work: Earth work, Rd construction. Footpath, sewerage, Sys, Stream water drain, water supply.
 No of Person  Employed:  192
 Name of Associated  Firm (s) Nil
 Total Project Cost:  Rs 2404.192 Mn
 Completion Date
Dec 2015
  • opf1
  • opf2
 
 
gomal
 

The main objective of the project is to provide sustainable irrigation water supply to 1, 63,100 acres of agricultural land so as to increase agricultural production and uplift the socio economic condition of the inhabitants. Upon completion, this project will satisfy 70% of agricultural requirements of DIK

and surroundings area.

 
Project Details

 Project Name:  Gomal Zam Dam (Irrigation Component)
 Project Location within  Country: FATA (KPK)
 Name of Client / Sponsor: WAPDA
 Consultant:  Management Consultant Wapda
 No of Plants Employed: 110
 Start Date (Month / Year): Jun 2008
     
 Country:  Pakistan
 Scoop of Work: Earth Work / Concrete Lining / Culverts
 No of Person  Employed:  663
 Name of Associated  Firm (s) Nil
 Total Project Cost:  Rs  3828 Mn
 Completion Date
Dec 2015
 
 
  • gomal
  • gomal1
lda
 
The scheme is developed for Government officers and shall provide quality living.
 
Project Details

 Proj Name:  LDA Ave I (GpII) Housing Scheme Lahore
 Proj Location within  Country: Lahore
 Name of Client / Sponsor: LDA
 Consultant:  DHA LHR
 No of Plants Employed: 6
 Start Date (Month / Year): Dec 2011
     
 Country:  Pakistan
 Scoop of Work: Sewerage Pumping Station R.C.C Drain & Other Allied Works in LDA Ave
 No of Person  Employed:  32
 Name of Associated  Firm (s) Nil
 Total Project Cost:  Rs 263 Mn
 Completion Date
Oct 2014
 
 
  • lda
  • lda1