PAF-Base

Rehabilitation of existing Taxi Track is of vital importance because after completion it will be used as second runway for aircrafts and commercial airlines. Along with taxi track, rehabilitation of 3x link roads are also being upgraded with same specification of runway. Now, PAF base will be effectively support to the operation towards Eastern border. Work is in full throttle and will complete in month time.

 

Project Details

 Project Name:  Rehabilitation of Parallel Taxi Track, PAF Base, Quetta
 Project Location within  Country: Quetta, Balochistan
Name of Client / Sponsor: M.E.S
 Consultant:  LRA
 No of Plants Employed: 120
 Start Date (Month / Year): Feb 2016
     
 Country:  Pakistan
 Scoop of Work: Rehabilitation of Taxi Track (12000 ft) and 3x link roads of 650 ft each with drain and 5 culverts
 No of Person  Employed:  147 persons
 Name of Associated  Firm (s)  
 Total Project Cost:  645.7 Mn
 Completion Date
Feb 2017