Details
-
Category: Completed Projects
-
Hits: 20553
The 57.77 Km two lane road will stretch from Wangu hill to Quba Saeed Khan. The new road will cut travel time, boost trade and the purpose of project is to link Gwadar Port with Indus Highway. This road will provide a convenient link between the two provinces. Respect for the local community is among the top concerns on the Khuzdar – Shahdadkot Road. Thinking locally makes good environmental impact as well as business sense and will leave a positive legacy of economic growth and a stronger skill base in the town.
The project was delayed due to super floods 2010, waterlogged & hard cutting area ,non aval of funds & addl works (VO-3) however rd & str works are mostly comp & subst completion for last 12 km has been applied.
Project Details
Project Name: |
Quba Saeed Khan (QSK) Khuzdar Shadad Kot (M-8) Section-IV Pakage (V) |
Project Location within Country: |
Sind Balochistan Khuzdar to Shadad Kot |
Name of Client / Sponsor: |
NHA |
Consultant: |
ACC (Pvt) Ltd |
No of Plants Employed: |
133 |
Start Date (Month / Year): |
June 2006 |
|
|
|
|
Country: |
Pakistan |
Scope of Work:
|
57.48 Km Road, 7 Diversions,10 Brigdes, 199 culverts, 2 Km R/wall |
No of Person Employed: |
194 |
Name of Associated Firm (s) |
Nil |
Total Project Cost: |
Rs 3056 Mn |
Completion Date
|
Jun 2016 |
|