Details
-
Category: BOT Projects
-
Hits: 2470
Detailed Narrative Description of the Project:
The 22.4 Km southern loop (SL 1 & SL 2) starts from Kamahan (DHA Ph V) and ends at Adda Plot, Raiwand Rd. The proj worth Rs 24,676 Mn is being executed by FWO on BOT basis. FWO will meet all const expenses and recover them through toll collection within 25 Yrs. The proj will benefit a large number of motorists daily in the busy area of Lahore. Chief Minister Punjab Mian Muhammad Shahbaz Sharif inaugurated the proj on 22 Dec 2017. Balance work is in full swing and expected to be completed by 30th July, 2018.
Project Details
Project Name: |
LRRP (Southern Loop) |
Project Location within Country: |
Lahore |
Name of Client / Sponsor: |
LRRA |
Consultant: |
NESPAK, ZEERAK/ BNA |
No of Plants Employed: |
221 Nos |
Start Date (Month / Year): |
Aug 2016 |
|
|
|
|
Country: |
Pakistan |
Scope of Work: |
Construction of 6 Lane Expressway provision of Intelligent Transportation System (ITS) for Northern & Southern Loop, Construction of 9.60 Km Svc Road, 6x Interchanges, 22 x Bridges & 66 x Culverts. |
No of Person Employed: |
516 |
Name of Associated Firm (s) |
Nil |
Total Project Cost: |
24,676 Mn
|
Completion Date
|
Mar 2018 |
|