Detailed Narrative Description of the Project:

Among the upcoming projects of FWO, Shogo - Sin Hydropower Project (HPP) is on top of the list on (BOOT) basis. Shogo - Sin HPP is located on Lutkho River, a tributary of Chitral River having capacity of 132MW. The multipurpose is intended to boost development in this remote area by enhancing irrigation, controlling the flash floods and producing cheap electricity. Thousands of jobs are also tied to producing crops grown with irrigated water. Among the upcoming projects of FWO, Shogo - Sin Hydropower Project (HPP) is on top of the list on (BOOT) basis. Shogo - Sin HPP is located on Lutkho River, a tributary of Chitral River having capacity of 132MW. The multipurpose is intended to boost development in this remote area by enhancing irrigation, controlling the flash floods and producing cheap electricity. Thousands of jobs are also tied to producing crops grown with irrigated water. In order to convert this dream into the reality, consultants (local plus foreign firms) have been engaged to update and revise the feasibility studies. Shogo Sin is on the top of the list, has been revised alongwith the drawing of the dam. Study has also been forwarded to PEDO for approval from panel of experts. On approval, NEPRA will be approached for generation license and tariff. After approval from NEPRA will be tenderized

 

Project Details

 Proj Name:

Shogo Sin Hydro Power (132 MW) Country:

 Pakistan

 Proj Location within Country:

Lutkho River, Chitral  Scope of Work:

EPC Contract – Civil Works

Name of Client / Sponsor:  

FWO No of Person Employed:

---

Consultant:

J & J Consultants
Pakistan Engineering Counsel (PES) Ltd
Name of Associated Firm (s), if any:

China National Electric Engineering Company (CNEEC)

 No of Plants Employed:      

--- Total Project Cost: 

332.33 Mn US $

 Start Date (Month / Year):

---  Completion Date (Month / Year):

-----

Construction Time : 

 54 Months  

 



 