RBOD-II is a mega drainage proj (273 KM) running along the Right Bank of River Indus. The drain will be connected to RBOD-I at Sehwan and will carry the effluent dir to sea at Gharo. RBOD-II Project Extension from Sehwan to sea (Mega project in Pakistan of 36 billion rupees and 3rd largest drain in the world). 31 Drainage units identified with covering area of 4.30 Million Acres are as under.
The designed disch of RBOD-II is 3525 Cusecs. WAPDA initially const disposal of the effluent into Manchar Lake. Indus Link was const for disposal into River Indus to avoid contamination of Manchar Lake. On the strong reservation of Sindh Govt on disposal in Indus River and the effected public in gen in Dist Badin, Hyderabad and Karachi, RBOD-II was planned. The proj commenced in 2001 but could not be exec as envisaged, FWO was incorporated on RBOD-II in Jun 06, on the abandoned proj. FWO by exploring all out efforts re-mob the contractors on all the earth work pkgs. Despite many hurdles like land acquisition, delayed design problems, law & order sit and flow rel of funds, FWO has done a great job and achieved progress up to 63.30% till to date.
Project delayed due to flooding area, limited vetting of work by cslt & non aval of funds. However, completion is expected before Jun 2017.

Project Details

 Project Name:  Ext of RBOD from Sehwan to Sea RBOD-II Project
 Project Location within  Country: Sehwan Sindh
Name of Client / Sponsor: Govt of Sindh
Consultant: MMP, ECIL, ABM & ACE
 Start Date (Month / Year): Jun  2006
     
 Country:  Pakistan
 Scope of Work:

Scope of Work:
273 Km Drain
557x Minor str, 18 x Med Str & 11 x Maj Str Earthwork Pkgs & Flood Protection Works

 Name of Associated  Firm (s)  
 Total Project Cost:  Rs 16794.298 Mn
 Completion Date
Dec  2016
 
  • RBOD
  • RBOD1