1.   RBOD-II is a mega drainage project (273 KM) running along the Right Bank of River Indus. The drain will be connected to RBOD-I at Sehwan and will carry the effluent directly to the sea at Gharo. RBOD-II Project Extension from Sehwan to sea (Megaproject in Pakistan of 36 billion rupees and 3rd largest drain in the world). 31 Drainage units identified with covering an area of 4.30 Million Acres are as under.1. RBOD-II is a mega drainage project (273 KM) running along the Right Bank of River Indus. The drain will be connected to RBOD-I at Sehwan and will carry the effluent dir to sea at Gharo. RBOD-II Project Extension from Sehwan to sea (Megaproject in Pakistan of 36 billion rupees and 3rd largest drain in the world). 31 Drainage units identified with covering an area of 4.30 Million Acres are as under.
2.   The designed discharge of RBOD-II is 3525 Cusecs. WAPDA initially constructed the disposal of the effluent into Manchar Lake. Indus Link was const for disposal into River Indus to avoid contamination of Manchar Lake. On the strong reservation of the Sindh Government on disposal in Indus River and the affected public in general in Dist Badin, Hyderabad, and Karachi, RBOD-II was planned. The project commenced in 2001 but could not be exec as envisaged. FWO was incorporated on RBOD-II on Jun 06, on the abandoned project.  FWO by exploring all our efforts re-mob the contractors on the earthwork package.  Despite many hurdles like land acquisition, delayed design problems, law & order sit and flow rel of funds, FWO has done a great job and achieved progress up to 67.30% to date. 
3.   Project delayed due to non-availability of funds, flooding area & limited vetting of work by Consultant. Now the work on a project is again delayed for the last 2 x quarters due to funds issues but the project seems to be completed in 2 x months if fund availability & PC 1 are approved.

Project Details

 Project Name:  Ext of RBOD from Sehwan to Sea RBOD-II Project
 Project Location within  Country: Sehwan Sindh
Name of Client / Sponsor: Govt of Sindh
Consultant: MMP, ECIL, ABM & ACE
 Start Date (Month / Year): Jun  2006
     
 Country:  Pakistan
 Scope of Work:

273 Km Drain
557x Minor str, 18 x Med Str & 11 x Maj Str Earthwork Pkgs & Flood Protection Works

 Name of Associated  Firm (s)  
 Total Project Cost:  Rs 16794.298 Mn
 Completion Date
Dec  2016
EOT Date Nov 2019