dha-lahore
 
Development of infrastructure and services of Phase - IX Defence Housing Authority Lahore was awarded to FWO in November 2011. The project includes 54 KM long roads, laying of water supply, sewerage, and electrical networks. The project is likely to be completed in November 2013. The state-of-the-art development of the area shall provide quality living to the families of martyrs of the armed forces.
 
Project Details

 Proj Name:  Development Works Ph-IX DHA Lahore
 Proj Location within  Country: Lahore
 Name of Client / Sponsor:  DHA Lahore
 Consultant:  DHA Lahore
 No of Plants Employed: 29
 Start Date (Month / Year): Nov 2011
     
 Country:  Pakistan
 Scope of Work: Const of Infra Structure Dev Work Rds Water Supply, Sewerage.
 No of Person  Employed:  312
 Name of Associated  Firm (s) Nil
 Total Project Cost:  Rs 1251 Mn
 Completion Date
Nov 2013