Detailed Narrative Description of the Project:

1. The Project has been 49% completed physically and is expected to be completed in April 2020. A large proportion of Pak Army officials belong to KPK. Their culture, traditions, and affiliation lie in their hometown. Before this, these Army officials were allotted plots mainly in Punjab, Sindh, and Baluchistan, consisting of 5 cities in which DHA operates.
2. CPEC introduction and terrorism elimination by 43% have begun to show effective results on the economy, deriving investors, multinational companies, and firms towards developer cities. So it will increase people's living standards and bring prosperity to KPK. 

 
Project Details

 Project Name:  DHA PSC PH-1 Sec-A
 Project Location within  Country: Peshawar (KPK)
 Name of Client / Sponsor:  
 Consultant:  NESPAK
 No of Plants Employed: 58 Nos
 Start Date (Month / Year): Dec 2019
     
 Country:  Pakistan
 Scope of Work: Construction of Road Work, Street Work, Sewerage & Water Supply
 No of Person Employed:  126
 Name of Associated  Firm (s) Nil
 Total Project Cost:  Rs 1773 Mn
 Completion Date
April 2020