Quick Impact Projects

 
Quick-Impact-Proj1  

Quick Impact Projects in South & North Waziristan Agency / Swat
Completed / Ongoing Projects

General

In the wake of successful op against terrorist, Government of Pakistan and US decided, to undertake development works in South Waziristan Agency (SWA) on fast track basis, Pakistan Army in consultation with Federal Administrated Tribal Areas FATA Secretariat identified three sectors namely Communication, Water and Power for this purpose. In this context a concept paper identifying the projects intended to be undertaken, proposed methodology for exec and cost effect was submitted to US Embassy on 25 Nov 2009.
A meeting was held at GHQ in Rawalpindi on 11 Dec 2009 b/w US Officials and Pakistan Army / FATA Officials wherein US authorities communicated that approximately US $ 53 M will be available for the Phase-I projects for which we need to identify and agree upon satisfactory utilization of Phase-I funds. Due to good pace of projects the Phase-I funding has been enhanced to US $ 132 M and US $ 288 M has been committed for Phase-II projects.
On the other hand, UAE - Pakistan Assistance Program (UAEPAP) was also commenced in Dec 2010 with the aim of communication sector development in FATA and Swat. It supplements the national counter terrorism strategy of “Dialogue, Deter & Develop. Through this US$ 121.63 M program in Phase-I & II, 2 x Bridges in Swat & 2 x Road in SWA & NWA have been completed in FATA.

Completed Projects

Location

Length

Comme-
ncement

Completion

  • USAID

 

 

 

 

  • Road Tank - Jandola - Makeen (TJM)

SWA

110 km

Jan 2010

Feb 2012

  • Road Tank - Gomal - Wana (TGW)

105 km

Feb 2010

Oct 2011

  • Road Wana - Shakai - Makeen (WSM)

76 km

Dec 2011

Dec 2013

  • Jandola Bridge on Road TJM

360 m

Jul 2011

Aug 2012

  • 8 x Bridges & 2 x Causeways on Road TJM

736 m

Sep 2012

Aug 2014

  • Gomal Bridge on Road TGW

136 m

Nov 2012

Jul 2014

  • Road Bannu - Miranshah - Ghulam Khan (BMG)

NWA

82 km

Jun 2011

Aug 2016

  • Road DI Khan - Hathala - Tank (DHT)

SWA

62 km

Aug 2012

Sep 2015

  • Road Pehawar - Landi Kotal - Torkham (PLT)

Khyber

52 km

Nov 2012

Aug 2015

  • Gomal Bridge on Road TGW

"

136 km

Nov 2012

Jul 2015

  • Dhana Irrigation & Water Supply Scheme

SWA

 

Oct 2012

May 2016

  • Gomal Zam Dam

 

 

 

 

  • Dam Component

SWA

 

Jun 2007

Sep 2013

  • Irrigation Component

 

-

Aug 2014

  • Power Sector

 

 

 

 

  • Wana Grid Station

SWA

 

Oct 2011

Dec 2013

  • Electric Restoration of 33 / 11 KVA lines (89 villages energized, 80 x 11 KVA & 9 x 33 KVA)

SWA

 

Jun 2010

Dec 2016

  • 132 KV Transmission Line from Gomal to Wana

46 km

Nov 2012

Mar 2015

  • INL (International Narcotics Law Enforcement Affairs)

 

 

 

 

  • Road Mattani - Takhtabaig (MTB)

Khyber

28 km

Mar 2015

Mar 2016

  • UAEPAP

 

 

 

 

  • HH Sheikh Khalifa Bin Zayed Al Nahyan Bridge

Swat

329 m

Jan 2011

May 2012

  • HH Sheikh Zayed Bin Sultan Al Nahyan Bridge

449 m

May 2011

Apr 2013

  • HH Sheikh Khalifa Bin Zayed Al Nahyan Road

SWA

50 km

Apr 2011

Jun 2013

  • Pak - Emirates Friendship Road (Road Miranshah - Razmak – Makeen)

NWA

72 km

Jun 2012

Apr 2016

Ongoing Projects

 

 

 

 

  • PSDP Funding Projects
       
  • Road Ghallanai - Mohmand Ghat (GMG)

Mohmand

40 km

Nov 2013

-

  • Nahakki Tunnel on Road GMG

"

751 m

Feb 2014

Dec 2016

         

 

PERMANENT RE-CONSTRUCTION PROJECTS (NWA / SWA)

General
In the wake of successful op (Zarb-e-Azb) against terrorist, Government of Pakistan undertake development works in South / North Waziristan Agency. Following projects of Rs 10,098.32 Million approved by Special Forum Committee for Re-construction / Rehabilitation of FATA,work has also commenced during June 2016

APPROVED PROJECTS

Location

Length

Completion

  • Internal City Roads of Miranshah

NWA

17.15 km

81%

  • Internal City Roads of Mir Ali

4.65 km

100%

  • Internal City Roads of Makeen

2.76 km

85%

  • Road Mir Ali-Ghariom-Dosali

57 km

63%

  • Road Miranshah - Datta Khel

41.2 km

71%

  • Road Dre Nishtar - Pash Ziarat - Razmak

71 km

35%
  • Road Wana Bazar

SWA

5 km

100%
  • Wana Bypass
SWA 8.7
36%
Projects in Planning Phases      
  • Road Zamchan - Dare Nishtar

SWA

10 km

Topo  Svy completed
  • Road Angoor Adda - Sarkanda - Zalai

38 km

Topo  Survey completed
  • Road Kotkai - Karama

40 km

-
  • Road Mana - Datta Khel

NWA

50 km

-
  • Road Ghariom - Razmak

"

22 km

-
  • Road Zarmilan - Zalai

SWA

40 km

 

 

 Quick-Impact-Proj2
 Quick-Impact-Proj3
 Quick-Impact-Proj4  
 Quick-Impact-Proj5  
 Quick-Impact-Proj6  
Quick-Impact-Proj7  
Quick-Impact-Proj8  
Quick-Impact-Proj9  
Quick-Impact-Proj10  
Quick-Impact-Proj11