Bridge of 1.20 KM over Indus River will provide a direct route from Rahim Yar Khan to Kot Mithan. Will link N - 5 to N - 55 on either side of river Indus. Will provide an alternate route between Punjab and Balochistan. When made fully functioned for traffic. Bridge has been successfully completed alongwith its ancillary works.
Project Details
Proj Name: |
Shaheed Benazir Bhutto Birdge on Indus river |
Proj Location within Country: |
Punjab Chercharan Sharif Pakistan |
Name of Client / Sponsor: |
NHA |
Consultant: |
REC – Loya JV |
No of Plants Employed: |
58 |
Start Date (Month / Year): |
Feb 2012 |
|
|
|
|
Country: |
Pakistan |
Scoop of Work: |
Construction of SBB Birdge |
No of Person Employed: |
Project completed |
Name of Associated Firm (s) |
Nil |
Total Project Cost: |
Rs 928 Mn |
Completion Date
|
May 2015 |
|