BOT Projects

 bot
lrrp main
 
Detailed Narrative Description of the Project:

The 22.4 Km southern loop (SL 1 & SL 2) starts from Kamahan (DHA Ph V) and ends at Adda Plot, Raiwand Road. The project worth Rs 23.476 Bn has been executed by FWO on BOT basis. The project was completed on 22 Dec 2017 (inaugurated by Chief Minister Punjab Mian Muhammad Shahbaz Sharif) and is presently operational with balance works in full swing which are likely to be completed shortly. The road is open for traffic and available to FWO for toll collection up to 25 Yrs. The project benefits a large number of motorists daily in the busy area of Lahore.

 
Project Details

 Project Name:  LRRP (Southern Loop)
 Project Location within  Country: Lahore
 Name of Client / Sponsor: LRRA
 Consultant:  NESPAK, ZEERAK/ BNA
 No of Plants Employed: -
 Start Date (Month / Year): Aug 2016
     
 Country:  Pakistan
 Scope of Work: Construction of 6 Lane Expressway provision of Intelligent Transportation System (ITS) for Northern & Southern Loop, Construction of 9.60 Km Svc Road, 6x Interchanges, 22 x Bridges & 66 x Culverts.
 No of Person Employed:  -
 Name of Associated  Firm (s) Nil
 Total Project Cost: 
23,476 Mn
 Completion Date
Jan 2020
 
 
  • Slide38
  • Slide41
  • lrrp-1
  • lrrp-2
  • lrrp-3
  • lrrp-4
  • lrrp-5
  • lrrp-6
  • lrrp-7
  • lrrp-8
  • lrrp-9
  • lrrp1
  • lrrp2
  • lrrp3
  • lrrp4
  • lrrp5
  • lrrp6
  • lrrp7
 kar hyd
 
The Karachi - Hyderabad Motorway (M-9) is a Six Lane, 136 KM long Motorway that connects two major cities Karachi & Hyderabad of Sindh province. The project is open for traffic and is the first project in Sindh province of its kind. The project includes the construction of several bridges, underpasses, interchanges, service road, fence and provision of ETTM/ITS facility. It will bring enormous economic benefit to the less developed parts of the country. Currently, balance works are in progress and will be completed shortly.

Project Details

 Project Name: 

KARACHI - HYDERABAD MOTORWAY (M-9)

 Project Location within  Country: Karachi to Hyderabad
Name of Client / Sponsor: NHA
 Consultant:  NESPAK
 Start Date (Month / Year): Nov 2018
     
 Country:  Pakistan
 Scope of Work:

136 Km main carriageway, 268 km Service Road,8x Interchanges (New) & 2 Interchanges (Existing), 11x Bridges, 19x Underpass, 518 x Culverts & Provision of ETTM/ITS System

 Name of Associated  Firm (s)  
 Total Project Cost:  6275 Mn
 Completion Date
Jul 2020
  • m-9-1
  • m-9-2
  • m-9-3
  • m-9-4
  • m-9-5
  • m-9-6
  • m-9-7
  • m-9-8
  • m-9-9
  • m-9-91
  • m-9-92
  • m-9-93
 
 
 swat exp
 

Detailed Narrative Description of the Project:

The construction of 81 Km long four lanes Expressway in the remote area of KPK is expected to become a transformative step for the province, generating tremendous benefits to its people and contributing towards development of the region. The Motorway will connect Karnal Sher Khan Interchange on (M-1) with Chakdara, tunneling its way through the mountain at Palai & Ala Dhand areas. 2 Km of the road falls in Distt Nowshera, 18 Km in Distt Swabi, 40 Km in Distt Mardan & 21 Km in Distt Malakand. The total ROW of the expressway is 80 mtrs. Work is in full swing expected to be completed by Sep 2020.

Project Details

 Project Name: 

Swat Expressway Project

 Project Location within  Country: KPK
 Name of Client / Sponsor: PKHA
 Consultant:  DD&C, OSMANI
 No of Plants Employed: 403
 Start Date (Month / Year): Nov 2016
     
 Country:  Pakistan
 Scope of Work: 7x Interchange, 26x Bridges/Flyover,37x Subways, 24x Cattle Creeps, 14x underpasses, 351x culverts & 3.7Kms  Twin Tube Tunnel 
 No of Person Employed: 1133
 Name of Associated  Firm (s) Nil
 Total Project Cost:  Rs 34,000 Mn
 Completion Date
Sep 2020
 
 
  • 1-swat-motorway
  • 10-swat-motorway
  • 11-swat-motorway
  • 12-swat-motorway
  • 2-swat-motorway
  • 3-swat-motorway
  • 4-swat-motorway
  • 5-swat-motorway
  • 6-swat-motorway
  • 7-swat-motorway
  • 8-swat-motorway
  • 9-swat-motorway
  • swat-1
  • swat-2
  • swat-3
 lsm 2
 

Detailed Narrative Description of the Project:

Lahore Sialkot Motorway is a 91.6 km long 4-lane Motorway with 28 bridges and 7 interchanges. Work on the project started in March 2017. Currently, Section-I (22 km long) is opened for public from Kala Shah Kaku to Muridke Interchange while overall project is expected to be completed in a few months. Once completed, the motorway will reduce the travel time between Sialkot and Lahore to just 50 minutes and will significantly reduce the traffic load on GT-road.

Project Details

 Project Name: 

Lahore Sialkot Motorway Project

 Project Location within  Country: Punjab
 Name of Client / Sponsor: NHA
 Consultant:  DD&C, ZEERUK & OSMANI-PAVRON (JV)
 No of Plants Employed: 230
 Start Date (Month / Year): Mar 2017
     
 Country:  Pakistan
 Scope of Work: 7x Interchanges, 2x Service Areas, 4x Layby Areas (Mini Service Area), 28 x Bridges, 23x Underpasses, 12x Subways, 34 x Cattle Creeps, 88 x Box culverts & 156 x Pipe Culverts
 No of Person Employed: 916
 Name of Associated  Firm (s) Nil
 Total Project Cost:   43.85 Bn
 Completion Date
June 2020
 
 
  • 1-lsm
  • 2-lsm
  • 3-lsm
  • 4-lsm
  • 5-lsm
  • 6-lsm
  • 7-lsm
  • 8-lsm
  • 9-lsm
  • 99-lsm
  • lsm-1
  • lsm-2
  • lsm-3
  • lsm-4
 NARAN HPP
 

Detailed Narrative Description of the Project:

It is proposed on the Kunhar River and would be producing 188MW of electricity. Naran Dam is a multipurpose project. It will create employment opportunities for the people of district Mansehra, KPK province during construction and after commissioning. Consortium of Local & International firms with FWO has been signed on 11th May’17. Evaluation of financial and technical bid has been completed. FWO has been declared as ‘First Rank Bidder’ and recommended to NEPRA for Letter of Award (LOA) on 23rd Oct 2017. Tariff Petition has also been submitted, now the project is under evaluation at NEPRA.

Project Details

 Proj Name:

NARAN HPP (188MW) Country:

 Pakistan

 Proj Location within Country:

Kunhar River, Mansehra Distt  Scope of Work:

EPC Contract – Civil Works

Name of Client / Sponsor:  

FWO No of Person Employed:

---

Consultant:

--- Name of Associated Firm (s), if any:

Wah Nobel 

KAIDI (CHINA)

 No of Plants Employed:

--- Total Project Cost: 

559 Mn US $

 Start Date (Month / Year):

---  Completion Date (Month / Year):

---

Construction Time: 51 Months